--Exposure B
· Stretch 1-3/4” line to alley opening
· Use line to wash wall of exposure B, reducing the effect of radiant heat
· Water should not enter any window
· Evacuate / primary search / secondary search of Exposure B
· Stretch additional 1-3/4” line into Exposure B to prevent against extension
· Close windows on exposed side, remove combustibles
· Open windows on unexposed side to dissipate heat build-up
· Coordinate engine and ladder operations
· Conduct salvage ops as required
· Control utilities as required
· Report conditions to Command
--Exposure D
· Evacuate / primary search / secondary search
· Stretch 1-3/4” line to top floor
· Open natural openings on roof
· Pull ceilings in coordination with roof team
· Horizontally vent windows as required
· Check for presence of shafts between buildings
o If present, Close windows on exposed side, remove combustibles
o Open windows on unexposed side to dissipate heat build-up
· Coordinate engine and ladder operations
· Report conditions to Command
All of the above including
· Assign Division B Supervisor
· Assign Division D Supervisor
· Assign Roof Division Supervisor
· Strike additional alarms as required
· Order additional water supplies as required
· Ensure tactical reserve is present at all times
· Ensure secondary egress in place in all areas
· Request Progress reports at regular intervals
· Reinforce Divisions as per conditions and Progress Reports
· Evaluate and modify action plan as per conditions and progress reports
· Furnish progress reports to Dispatch at regular intervals
· Conduct roll call
· Track company activities on tactical worksheet ands Command Board